If your land is tight, YUSHUNXIN also can offer customized high-efficiency BB fertilizer production solutions. It will designed with a compact pit-type layout or vertical conveying.
When you plan to set up a blended fertilizer manufacturing plant, land area is an aspect must pay attention to. In general, with a standard fertilizer mixing system of 1-100TPH, you need to prepare an area of 500-2000 ㎡. It usually contains zone for bulk blending fertilizer making line, materials storage, bagged fertilizer palletizing. If you need to produce BB fertilizer in a limited area, there are also customized solutions with reasonable design. Such as pit-type layout, bucket lift convey, etc. Welcome to inquiry YUSHUNXIN for your own blend fertilizer making process.
Get Free QuoteTo make your bulk blending fertilizer system works efficiently all year, it is necessary to split the land into required functional sections.
Normally, there are 3 main zones in the workshop for a bulk blending fertilizer making plant. Powder and granular raw material storage, fertilizer blending system installation and finished BB fertilizer in stock.
But, if you plan to extend you fertilizer production business, it is advisable to reserve space for future silos, extra batching bins, or an additional fertilizer mixing unit. So, you can upgrade output without changing the land needed by a blended fertilizer manufacturing plant.
Get a Free Quote
With a standard configuration, the land needed by a blended fertilizer manufacturing plant mainly depends on capacity. Commonly, for 1-100TPH operations, you need to prepare a workshop land of 500-2000 ㎡.
A 1–10 TPH BB fertilizer production line often fits in 500–800 ㎡. For this, you still arrange separate zones for raw material bins, batching and mixing area, and bagging station.
For 10–50 TPH fertilizer blending systems, you usually prepare 800–1,500 ㎡. Since you need more space for urea, MAP, DAP, KCL, fillers, trace element additives, and finished fertilizer pallets.
When you design a 50–100 TPH continuous BB fertilizer blending project solution, the land needed by a blended fertilizer manufacturing plant generally reaches 1,500-2,000 ㎡. Because you must include weighing hoppers, multi-bin batching systems, automatic bagging lines, and truck loading areas in one complete layout.
If you plan your receiving area, internal traffic, and warehouse height properly, you often reduce the total land needed by a blended fertilizer manufacturing plant, and you still keep good material flow and flexible operation.
If your land is tight, YUSHUNXIN also can offer customized high-efficiency BB fertilizer production solutions. It will designed with a compact pit-type layout or vertical conveying.
You may use pit-type layout for your fertilizer blending system. where you place receiving hoppers and batching systems underground, so you shorten conveyor length and save ground space
In addition, you can install bucket elevator conveying between batching bins and fertilizer mixer and between mixer and automatic bagging scale. Therefore, you use vertical space and reduce the footprint of your blend fertilizer making process.
If you want a tailored design for your own BB fertilizer project, welcome to contact YUSHUNXIN now! Besides land, we will design blend fertilizer making solutions according to your capacity, budget, materials, etc. Such as 30 TPH BB fertilizer production plans, $200,000 cost fertilizer mixing system, npk fertilizer blending lines, compost fertilizer mixing unit and more.
Leave Your Message
FREE CONSULTATION
Get You Customized Fertilize
Blending Project Solution Now!

Leave Your Message
Free Quote
Free Quote
English